How long contractor permits take to close, by city

As of November 17, 2026, the typical contractor's electrical permit was signed off 87 days after it was issued (median across 11 US cities), from 37 days in Bellevue, WA to 122 days in Honolulu, HI. Building permits took from 36 days in Orlando, FL to 238 days in Cincinnati, OH.

A permit stays open until the city signs off the finished work, usually at a final inspection. Until then, the job is not closed in the city's records. These are the typical times for permits that did close; they include waiting for the work itself, for inspections and for any re-inspection. If your permit is still open well past the time for your city, ask the contractor to book the final inspection.

Typical days from permit issue to sign-off, by city and kind of permit
CityBuildingElectricalPlumbingMechanical (HVAC)Fire sprinklers
Austin, TX–7191116–
Bellevue, WA–3791––
Cincinnati, OH238–80160202
DeKalb County, GA–68–––
Honolulu, HI235122–––
Mesa, AZ206––––
Miami, FL9590121105–
Orlando, FL36658474–
Philadelphia, PA221101133188–
Phoenix, AZ78––347186
Raleigh, NC–92132120142
Saint Paul, MN7852–––
San Francisco, CA1158776––
Seattle, WA–––96–
Somerville, MA127100–––

A dash means fewer than 30 contractors had enough signed-off permits of that kind, or the city does not record a completion date. Each contractor's own median time is on its record, by kind of permit. Permits that never closed: permits that expire without a final inspection.

Download the table: CSV · JSON (counts only, with column notes; CC BY 4.0).

How this was counted

Permits issued since November 19, 2021 to contractors Swapwire holds a record for, matched by license number or exact business name as each city file allows, that the city marks completed (finaled or signed off) with a completion date. Days run from the issue date to that date. Each contractor with at least 10 completed permits of a kind gets its own median; the figure shown is the middle of those medians, so it describes the typical contractor, not every permit. Cities need 30 such contractors for a kind to be shown. Permits still open, cancelled or expired are not counted, so a recent permit that closed quickly counts while a slow one issued at the same time does not yet: the figures run a little short. Cities define completion in their own way, so compare kinds of permit within a city before comparing cities.