Contractor rules in Florida: deposits, licenses and permits
Florida sets no flat dollar or percent cap on a contractor's deposit. If a contractor takes an initial payment of more than 10 percent of the contract price on a residential job, they must apply for the needed permits within 30 days and start work within 90 days after the permits are issued, or face criminal penalties. Florida licenses contractors through the DBPR Construction Industry Licensing Board; work of a 'casual, minor, or inconsequential' nature under $2,500 total is exempt, and plumbing, air-conditioning, roofing, sheet metal, mechanical and general building contractors are licensed categories. Electrical contracting is licensed under a separate part of the same chapter.
- Down payment limit
- When a license is required
- What a handyman may do
- Permits for common jobs
- Who can pull permits
- Bonds and insurance
- Contracts and your right to cancel
- Check a license
Down payment limit
Florida sets no flat dollar or percent cap on a contractor's deposit. If a contractor takes an initial payment of more than 10 percent of the contract price on a residential job, they must apply for the needed permits within 30 days and start work within 90 days after the permits are issued, or face criminal penalties.
- Deposit trigger: 10%
- Permit application deadline: 30 days
- Start work deadline days after permits: 90
- Demand response: 30 days
Conditions
- Applies to residential repair, restoration, improvement or construction contracts (Fla. Stat. 489.126(2)(a)).
- No permit application is required in the 30 days if no permit is needed.
- If the contractor does not comply, the owner sends a written demand by certified mail, return receipt requested; no action within 30 days of the demand can support an inference the contractor had no just cause (489.126(2)(b)).
- Separately, a contractor may not refuse or fail to perform for 90 days when payments exceed the value of work done (489.126(3)).
Exceptions
- Not a violation if the contractor has just cause, or the owner agreed in writing to a longer period.
- The section does not mention special-order materials.
Sources:
Checked .
When a license is required
Yes. Florida licenses contractors through the DBPR Construction Industry Licensing Board; work of a 'casual, minor, or inconsequential' nature under $2,500 total is exempt, and plumbing, air-conditioning, roofing, sheet metal, mechanical and general building contractors are licensed categories. Electrical contracting is licensed under a separate part of the same chapter.
- Minor work exemption usd less than: 2,500
Conditions
- Licensed categories named in 489.105(3) include general, building, residential, sheet metal, roofing, air-conditioning (Class A, B, C), mechanical, pool/spa, plumbing, underground utility, solar, pollutant storage.
- A certified contractor may work statewide; a registered contractor only in the places where registered (489.105(8), (10)).
- An unlicensed contractor's contract is unenforceable by the contractor if a license was required for the scope of work (489.128).
- Working without a required building permit is itself prohibited (489.127(1)(h)).
Exceptions
- Minor work exemption does not apply if the job is part of a larger project, is split into contracts under $2,500 to evade the law, or the person advertises as a contractor (489.103(9)).
- Other exemptions include owner-builders (489.103(7)), employees of licensed firms, material-only suppliers and sheds up to 250 sq ft.
Sources:
- Fla. Stat. 489.103
- Fla. Stat. 489.105
- Fla. Stat. 489.128
- Fla. Stat. 489.127
- Fla. Stat. 489.503 (electrical contracting exemptions)
Checked .
What a handyman may do
Florida has no handyman license. An unlicensed person may do casual, minor work only if the whole job (labor, materials and everything else) is under $2,500, it is not part of a larger project, and they do not advertise as a contractor. Plumbing, electrical and air-conditioning work is not covered by DBPR's no-license examples. Drywall alone needs no license, and neither does painting, according to DBPR, unless the job also includes load-bearing wall, plumbing, electrical or air-conditioning work.
- Max job usd less than: 2,500
Conditions
- Drywall: DBPR says installing or replacing drywall needs no license unless the contract also includes work on a load-bearing part of the wall, plumbing, electrical, or air conditioning work.
- Painting: DBPR says painting needs no license regardless of compensation (also cabinets, wood or tile flooring, insulation).
- DBPR says its examples are not all-inclusive; for a specific job call DBPR at 850.487.1395.
- A contractor is anyone who demolishes, subtracts from, builds or improves a building or structure for compensation (DBPR page).
Exceptions
- Advertising as a contractor, splitting a job into pieces under $2,500, or doing part of a bigger job all lose the exemption (489.103(9)).
- Drywall rule above answers the question 'do I need a license for drywall in Florida': usually no, if it is drywall alone.
Sources:
Checked .
Permits for common jobs
The Florida Building Code is adopted statewide, but permits are issued and enforced by cities and counties. Doing work that needs a permit without one is prohibited for a contractor, and the lists of exempt jobs are set locally (see each city).
Conditions
- The Florida Building Commission adopts the code by rule (Fla. Stat. 553.73(1)(a)).
- Commencing work that needs a building permit without the permit in effect is a prohibited act for a person acting as a contractor (489.127(1)(h)).
Exceptions
- Swapwire did not confirm a statewide list of permit-exempt jobs; use the local building department.
Miami
Permits: City of Miami Residential Permit Guide (iBuild portal for applications)
Page does not mention decks or electrical panels. Easy Permit is contractor-only; owner-builders have a separate path (https://www.miami.gov/Permits-Construction/Remodeling-and-Construction/Become-an-Owner-Builder, linked from the guide).
- Water heater replacement: The City of Miami lists 'Water Heater-Replacement Only' as an electrical Easy Permit, 'Change Out: Water Heater' as a plumbing Easy Permit and 'Replacement Only: Water Heater' as a gas Easy Permit, so a replacement is a permitted job; Easy Permits are for qualified contractors in good standing. [source]
- Furnace, AC or heat pump replacement: The city lists 'Replace Same Location Central AC/Heating System' and 'A/C Change Out' as Easy Permit types; mechanical Easy Permits are limited to like-for-like equipment. [source] [source]
- Roof replacement: The City of Miami's Residential Permit Guide lists residential reroofing (for example 'Reroofing - Shingle Roof') as a permit type handled through its Homeowners Express Review. [source]
- Fence: Fences up to 6 feet are listed under the city's Walk-Thru Express Residential permit; fences above 6 feet need structural review. [source]
- Bathroom remodel: Bathroom fixture change-outs (lavatory, bathtub, bidet, toilet, urinal, shower pan, exhaust fan) are listed as Easy Permit items, so they are permitted work. [source]
Miami-Dade County
Permits: Miami-Dade County: How to Apply for a Permit (also Permit Exemptions page)
Exemptions apply to Florida Building Code permits only; zoning and other approvals may still be required. Page scope is unincorporated Miami-Dade County. Permits are issued in the name of the person doing the work; only licensed contractors or owner-builders may obtain one.
- Water heater replacement: Miami-Dade's permit page says replacing a hot water heater requires a permit. Its exemptions list (unincorporated county) says replacing an electric water heater of 4,500 watts or less and up to 50 gallons is exempt from the electrical permit, but a permit is required if the new unit's wattage is higher. [source] [source]
- Roof replacement: Miami-Dade's permit page says a new roof needs a permit; reapplying a roof maintenance coating is exempt, but waterproofing roof coatings need a permit. [source] [source]
- Fence: In unincorporated Miami-Dade, non-wind-resistant fences such as chain-link or picket are exempt from a building permit but still need a zoning permit; wind-resistant fences need a building permit. [source]
- Deck: Wood decks 18 inches or less above ground are exempt from a building permit (for single-family, duplex, townhouse and condo units, within the page's $5,000 per 12 months cap on such items). [source]
Orlando
Permits: City of Orlando Residential Permitting Requirements (plans via ProjectDox)
Residential guide says permits are required for most construction and trade permits are required for electrical, plumbing, gas or other work; owner doing own work signs an Owner/Builder Declaration in person at Permitting Services; a recorded Notice of Commencement is needed when construction value exceeds $5,000. Water heater, AC, deck, bathroom and panel rules not found on the pages read.
- Roof replacement: Orlando issues a residential re-roof permit and requires a dry-in (in-progress) inspection and a final inspection with an inspection affidavit for residential re-roofs. [source]
- Fence: No fence permit is needed if the fence is on a one- or two-family lot, 6 feet or less, outside a historic district, made of wood, vinyl, chain-link, aluminum, wrought iron or plants, and meets overlay rules. A permit is required for fences in historic districts, on commercial or 3+ unit lots, over 6 feet, or of concrete or masonry. [source]
Sources:
Checked .
Who can pull permits
A Florida homeowner may act as owner-builder on their own one- or two-family home (or a farm outbuilding) if they apply for the permit, sign in person, directly supervise the work, and do not offer the property for sale or lease. Selling or leasing within 1 year after completion is presumed to mean it was built for sale.
- Sale presumption: 12 months
- Commercial owner builder max: $75,000
Conditions
- Owner must personally appear and sign the permit application and sign a disclosure statement covering employer duties such as tax withholding and workers' compensation.
- Direct onsite supervision of work not done by licensed contractors cannot be delegated to anyone not licensed for that work.
- Electrical: an owner may act as their own electrical contractor on a single-family or duplex residence for own use and occupancy (489.503(6)(a)).
- Local rule: Miami-Dade says permits go in the name of the person doing the work and only licensed contractors or owner-builders may obtain one; Orlando requires an Owner/Builder Declaration signed in person.
Exceptions
- The owner-builder exemption does not cover anyone the owner employs who acts as a contractor (489.503(6)(c)).
Sources:
- Fla. Stat. 489.103
- Fla. Stat. 489.503(6)
- Miami-Dade: How to Apply for a Permit
- City of Orlando Residential Permitting Requirements
Checked .
Bonds and insurance
To get or renew a Florida contractor certificate or registration, the applicant must file an affidavit that they carry workers' compensation, public liability and property damage insurance, in amounts set by Construction Industry Licensing Board rule. Initial certification also requires a credit report and evidence of financial responsibility.
Conditions
- The statute does not state dollar amounts for insurance; the board sets them by rule (Swapwire did not read the rule).
- Fla. Stat. 489.126 (deposits) and the recovery fund provide homeowner protection instead of a statutory bond.
Sources:
Checked .
Contracts and your right to cancel
Florida requires a written Homeowners' Construction Recovery Fund notice in every residential repair, improvement or construction contract worth more than $2,500. A sale made at your home by a seller who solicited you for more than $25 can be cancelled until midnight of the third business day.
- Recovery fund notice threshold: $2,500
- Cancel days business: 3
- Home solicitation threshold: $25
Conditions
- Recovery fund statement text is set by 489.1425(1); fines for omitting it: up to $500 first violation, $1,000 per later violation.
- Home solicitation sales must be in writing with a 'BUYER'S RIGHT TO CANCEL' statement; the seller may not keep all or part of any cash down payment if you cancel (501.031).
- Federal Cooling-Off Rule also applies to door-to-door sales of $25 or more (16 CFR 429).
Exceptions
- Recovery fund notice not required when all labor and materials do not exceed $2,500.
- Federal rule excludes a buyer-initiated visit to repair personal property and emergency work with a handwritten waiver.
Sources:
- Fla. Stat. 489.1425
- Fla. Stat. 501.021
- Fla. Stat. 501.031
- 16 CFR 429.0 and 429.1 (FTC Cooling-Off Rule), eCFR
Checked .
Check a license
Check a Florida contractor at DBPR's MyFloridaLicense 'Verify a Licensee' search; the department's Construction Industry page lists license types and workers' compensation status tools.
Sources:
Checked .
More
- How to check a contractor license in Florida
- Problems with a contractor in Florida: complaints, bonds and recovery
- The same rules as JSON: /data/rules.json, or the
get_rulestool on the Swapwire MCP server.
Common questions
How much can a contractor ask up front in Florida?
Florida sets no flat dollar or percent cap on a contractor's deposit. If a contractor takes an initial payment of more than 10 percent of the contract price on a residential job, they must apply for the needed permits within 30 days and start work within 90 days after the permits are issued, or face criminal penalties.
When does a contractor need a license in Florida?
Yes. Florida licenses contractors through the DBPR Construction Industry Licensing Board; work of a 'casual, minor, or inconsequential' nature under $2,500 total is exempt, and plumbing, air-conditioning, roofing, sheet metal, mechanical and general building contractors are licensed categories. Electrical contracting is licensed under a separate part of the same chapter.
Can a handyman work without a license in Florida?
Florida has no handyman license. An unlicensed person may do casual, minor work only if the whole job (labor, materials and everything else) is under $2,500, it is not part of a larger project, and they do not advertise as a contractor. Plumbing, electrical and air-conditioning work is not covered by DBPR's no-license examples. Drywall alone needs no license, and neither does painting, according to DBPR, unless the job also includes load-bearing wall, plumbing, electrical or air-conditioning work.
Do I need a permit in Florida?
The Florida Building Code is adopted statewide, but permits are issued and enforced by cities and counties. Doing work that needs a permit without one is prohibited for a contractor, and the lists of exempt jobs are set locally (see each city).
Can a homeowner pull their own permit in Florida?
A Florida homeowner may act as owner-builder on their own one- or two-family home (or a farm outbuilding) if they apply for the permit, sign in person, directly supervise the work, and do not offer the property for sale or lease. Selling or leasing within 1 year after completion is presumed to mean it was built for sale.
What bond and insurance must a Florida contractor carry?
To get or renew a Florida contractor certificate or registration, the applicant must file an affidavit that they carry workers' compensation, public liability and property damage insurance, in amounts set by Construction Industry Licensing Board rule. Initial certification also requires a credit report and evidence of financial responsibility.
What must a home improvement contract include in Florida?
Florida requires a written Homeowners' Construction Recovery Fund notice in every residential repair, improvement or construction contract worth more than $2,500. A sale made at your home by a seller who solicited you for more than $25 can be cancelled until midnight of the third business day.
Where do I check a contractor license in Florida?
Check a Florida contractor at DBPR's MyFloridaLicense 'Verify a Licensee' search; the department's Construction Industry page lists license types and workers' compensation status tools.
Sources
- Fla. Stat. 489.126
- Fla. Stat. 489.103
- Fla. Stat. 489.105
- Fla. Stat. 489.128
- Fla. Stat. 489.127
- Fla. Stat. 489.503 (electrical contracting exemptions)
- DBPR: Services Requiring a DBPR License
- Fla. Stat. 553.73
- Miami-Dade: How to Apply for a Permit
- City of Orlando Residential Permitting Requirements
- Fla. Stat. 489.115
- Fla. Stat. 489.1425
- Fla. Stat. 501.021
- Fla. Stat. 501.031
- 16 CFR 429.0 and 429.1 (FTC Cooling-Off Rule), eCFR
- MyFloridaLicense.com license search (Verify a Licensee)
- DBPR Construction Industry
Last reviewed ; data as of . General information, not legal advice. Rules change: the licensing agency has the final word.