Contractor rules in Oregon: deposits, licenses and permits
Oregon's construction contractor law (ORS 701) sets no cap on deposits. If a contractor takes a deposit of more than 50 percent of the contract price for a home improvement and then fails to perform or fails to return it within 10 days of a reasonable demand, the CCB may put the contractor on probation. In Oregon, anyone who does contractor work must have a current CCB license with an endorsement; residential work must be done under one of the residential endorsements. Work under $1,000 on one project of a casual, minor nature is exempt if the person does not advertise as a contractor.
- Down payment limit
- When a license is required
- What a handyman may do
- Permits for common jobs
- Who can pull permits
- Bonds and insurance
- Contracts and your right to cancel
- Check a license
Down payment limit
Oregon's construction contractor law (ORS 701) sets no cap on deposits. If a contractor takes a deposit of more than 50 percent of the contract price for a home improvement and then fails to perform or fails to return it within 10 days of a reasonable demand, the CCB may put the contractor on probation.
- Probation trigger deposit pct more than: 50
- Return deposit: 10 days
Conditions
- Applies to a contractor who offers to perform a home improvement and accepts a deposit of more than 50 percent of the total contract price (ORS 701.312).
- Swapwire searched the full text of ORS ch. 701 and found no other deposit or down payment limit.
Exceptions
- This is a probation ground, not a ban on larger deposits.
Sources:
Checked .
When a license is required
Yes. In Oregon, anyone who does contractor work must have a current CCB license with an endorsement; residential work must be done under one of the residential endorsements. Work under $1,000 on one project of a casual, minor nature is exempt if the person does not advertise as a contractor.
- Minor work exemption usd less than: 1,000
Conditions
- License required (ORS 701.021(1)); work on residential structures must be done under a residential endorsement (701.021(2)).
- Electrical installations need an electrical license except as exempted (ORS 479.540); plumbing contractors need a plumbing contractor license (ORS 447.040).
Exceptions
- Exempt: one structure or project with aggregate price under $1,000, casual/minor/inconsequential, and no advertising or sign or card suggesting contractor status (701.010(4)).
- Exempt: a person working on property they own or on their own residence (701.010(7)); owners hiring licensed contractors (701.010(5)-(6)).
Sources:
Checked .
What a handyman may do
A handyman in Oregon needs a CCB license for any project of $1,000 or more, and may not advertise (including a card, sign or other device) as a contractor without one. Electrical and plumbing work have their own license rules.
- Max job usd less than: 1,000
Conditions
- The $1,000 is the total price of all contracts for labor, materials and everything else on one structure or project, and the work must be casual, minor or inconsequential (ORS 701.010(4)).
- Electrical installations require an electrical license unless it is the owner or immediate family's own residential/farm property not for sale, rent, lease or exchange (ORS 479.540(1)).
- Plumbing: may not work or advertise as a plumbing contractor without a plumbing contractor license (ORS 447.040).
Exceptions
- Plumbing licensing does not apply to plumbing work not done for hire (ORS 447.060(1)(a)).
Sources:
Checked .
Permits for common jobs
Oregon requires local permits for a range of installations, alterations and construction; permits come from the local building department, and the state sets the building codes (the Oregon Residential Specialty Code, with its 2026 Chapter 1 effective October 1, 2026). A water heater replacement requires a plumbing permit.
- Permit expires if not started: 180 days
Conditions
- Permits are issued by local building departments; the person doing the work, homeowner or contractor, is responsible for obtaining the permits (BCD).
- A homeowner or firm doing plumbing work must get a permit for water heater replacement; a hired plumbing contractor may use a streamlined 'minor label' permit (BCD).
- Installing or altering permanent wiring or devices needs an electrical permit; like-for-like outlet, light fixture or switch replacement does not (BCD).
- Permit expires if work is not started within 180 days (BCD).
- Creating new habitable space, new toilet rooms or new bathrooms in structures not exempt requires a building permit (ORSC R105.1.1).
Exceptions
- Local municipalities may still apply their own ordinances; separate plumbing, electrical and mechanical permits may be required even for work exempt from the structural permit (ORSC R105.2).
Statewide, by job
- Water heater replacement: A permit is required to replace a water heater. A hired plumbing contractor may use a streamlined minor label permit. [source]
- Roof replacement: Reroofing, including replacing damaged sheathing, needs no structural permit when the added dead load is 4 psf or less, except for townhouses and attached stacked two-family dwellings, building-integrated photovoltaic roofing, and where original construction had to meet the wildfire standard (R327) by local adoption. [source]
- Deck: No structural permit for decks and porches attached to or serving a regulated building when the walking surface is not more than 30 inches above grade, and for detached platforms and decks not more than 30 inches above grade (any size). [source]
- Bathroom remodel: Creating a new bathroom or toilet room in a structure that is not exempt needs a building permit; painting, tiling, cabinets and countertops need none, though plumbing, electrical or mechanical permits may still apply. [source]
- Electrical panel replacement: Installing or altering permanent wiring needs an electrical permit; the BCD page excludes only like-for-like replacement of outlets, light fixtures and switches. Panel replacement is not named on the page, so treat it as needing a permit and confirm locally. [source]
Sources:
- Oregon BCD: About Oregon residential building permits
- 2026 ORSC Chapter 1 (effective Oct. 1, 2026), R105
- ORS 455.020
Checked .
Who can pull permits
In Oregon, the person doing the work, whether homeowner or contractor, must get the permit. A homeowner may do electrical work on their own residential property (or an immediate family member's) without a license if it is not for sale, rent, lease or exchange, but must still follow permit and inspection rules.
Conditions
- BCD: 'The person performing the work, whether it is a homeowner or contractor, is responsible for obtaining all necessary permits'; a homeowner or firm doing plumbing must obtain a permit.
- Electrical exemption does not exempt the work from ORS ch. 455 or ch. 479 requirements (ORS 479.540(1)(a)).
- A person working on their own property or residence is exempt from CCB licensing (ORS 701.010(7)).
- Owner-built dwellings and outbuildings built entirely by the owner (or unpaid friends and relatives) who will occupy them are exempt from some structural code provisions such as ceiling heights and room sizes (ORS 455.320).
Exceptions
- For rented, leased or sale properties the electrical owner exemption covers only maintenance and certain like-for-like replacements.
Sources:
Checked .
Bonds and insurance
Oregon residential contractors must carry a surety bond and general liability insurance: residential general $25,000 bond and $500,000 insurance; residential specialty $20,000 and $300,000; residential limited $15,000 and $100,000.
- Residential general bond: $25,000
- Residential general insurance: $500,000
- Residential specialty bond: $20,000
- Residential specialty insurance: $300,000
- Residential limited bond: $15,000
- Residential limited insurance: $100,000
Conditions
- Each residential contractor also needs a responsible managing individual (ORS 701.081).
- CCB: bond amounts rose $5,000 for each endorsement type effective January 1, 2024.
Sources:
Checked .
Contracts and your right to cancel
In Oregon a contractor needs a written contract for residential work priced over $2,000, and the homeowner may cancel an initial written contract by midnight at the end of the next business day. The contract cannot limit your right to file a complaint with the CCB.
- Written contract threshold usd over: 2,000
- Cancel period: until midnight of the next business day
- Late contract delivery: 5 days
Conditions
- If a job starts under $2,000 and goes over, the contractor must deliver a written contract within 5 days of knowing (ORS 701.305(1)); not having one does not void the contract.
- The CCB sets standard contractual terms for contracts requiring a written contract (701.305(2)).
- Cancel by written notice (including email) (ORS 701.310(1)).
Exceptions
- No cancellation if both parties agree work begins before the period ends, after substantial work has begun, or when modifying an initial contract after the cancellation period (701.310(2)).
- The federal Cooling-Off Rule also applies to door-to-door sales of $25 or more.
Sources:
Checked .
Check a license
Check an Oregon contractor on the CCB's license search.
Sources:
Checked .
More
- How to check a contractor license in Oregon
- Problems with a contractor in Oregon: complaints, bonds and recovery
- The same rules as JSON: /data/rules.json, or the
get_rulestool on the Swapwire MCP server.
Common questions
How much can a contractor ask up front in Oregon?
Oregon's construction contractor law (ORS 701) sets no cap on deposits. If a contractor takes a deposit of more than 50 percent of the contract price for a home improvement and then fails to perform or fails to return it within 10 days of a reasonable demand, the CCB may put the contractor on probation.
When does a contractor need a license in Oregon?
Yes. In Oregon, anyone who does contractor work must have a current CCB license with an endorsement; residential work must be done under one of the residential endorsements. Work under $1,000 on one project of a casual, minor nature is exempt if the person does not advertise as a contractor.
Can a handyman work without a license in Oregon?
A handyman in Oregon needs a CCB license for any project of $1,000 or more, and may not advertise (including a card, sign or other device) as a contractor without one. Electrical and plumbing work have their own license rules.
Do I need a permit in Oregon?
Oregon requires local permits for a range of installations, alterations and construction; permits come from the local building department, and the state sets the building codes (the Oregon Residential Specialty Code, with its 2026 Chapter 1 effective October 1, 2026). A water heater replacement requires a plumbing permit.
Can a homeowner pull their own permit in Oregon?
In Oregon, the person doing the work, whether homeowner or contractor, must get the permit. A homeowner may do electrical work on their own residential property (or an immediate family member's) without a license if it is not for sale, rent, lease or exchange, but must still follow permit and inspection rules.
What bond and insurance must a Oregon contractor carry?
Oregon residential contractors must carry a surety bond and general liability insurance: residential general $25,000 bond and $500,000 insurance; residential specialty $20,000 and $300,000; residential limited $15,000 and $100,000.
What must a home improvement contract include in Oregon?
In Oregon a contractor needs a written contract for residential work priced over $2,000, and the homeowner may cancel an initial written contract by midnight at the end of the next business day. The contract cannot limit your right to file a complaint with the CCB.
Where do I check a contractor license in Oregon?
Check an Oregon contractor on the CCB's license search.
Sources
- ORS 701.312
- ORS 479.540
- ORS 447.040
- Oregon BCD: About Oregon residential building permits
- 2026 ORSC Chapter 1 (effective Oct. 1, 2026), R105
- ORS 455.020
- Oregon CCB: Licensing
- 16 CFR 429.0 and 429.1 (FTC Cooling-Off Rule), eCFR
- Oregon CCB license search